Is there any possibility that the tasks in PE could be auto filled, for example if we complete stage 4 can PE not automatically update 1-3 without having to manually complete each section?
Date
Votes
1 comment
-
Michelle Harris Hi Susan
This is possible. If you set the Predecessor on a task to be an earlier task - when the later task is completed it will also mark any predecessor tasks as complete.
Thanks
Michelle
Please sign in to leave a comment.